When a new building, office or workshop is commissioned, you need documents proving the electrical installation is safe. Those documents are test reports from an accredited laboratory. Here is a short guide to which tests are done and what each one checks.
- Handover requires 5 main tests: insulation, earthing, bonding continuity, earth fault loop, RCDs.
- Each test is recorded in its own report, issued by an accredited laboratory.
- In a 380/220 V network, automatic disconnection at 220 V must take no more than 0.4 seconds (PUE table 1.7.1).
1. Insulation resistance
All circuits, panels and cables are tested with a megohmmeter. For installations up to 1 kV the minimum is 0.5 MΩ. More: insulation resistance limits.
2. Earthing resistance
The building's earth electrode system and lightning protection earthing are tested. The required value depends on the network system. More: earthing limits.
3. Bonding continuity
We check that panels, cable trays, pipes and equipment enclosures are reliably connected to the earthing system. A broken or rusty connection leaves a dangerous voltage on the enclosure during a fault.
4. Earth fault loop impedance
This test shows whether a breaker will trip fast enough during a short circuit. If the loop impedance is high, the fault current is low and the breaker trips late. Under PUE table 1.7.1, in a TN system disconnection must take no more than 0.4 s at 220 V and 0.2 s at 380 V.
5. RCD testing
For each RCD we check at what leakage current and how quickly it trips. The RCD is the main protection against electric shock, so pressing the Test button is not enough.
Reports and timing
All tests are done in one visit, each with its own report. The Enerji Test Servis LLC laboratory is accredited to AZS ISO/IEC 17025:2020. On larger sites, 6–10 kV cables also need high-voltage testing.
Earthing tests — Enerji Test Servis
FAQ
Are these tests needed for a flat?
For a new flat or a full rewire, insulation, earthing and RCD tests are recommended. We agree the list for each property.
When will the reports be ready?
Usually within a few working days of the tests. We give the timing upfront, based on the size of the job.
Will the power be switched off?
Circuits are briefly disconnected for insulation testing. Most other tests are done live. We agree the schedule in advance.
What kinds of sites do you work on?
Residential buildings, offices, shopping centres, industrial sites and substations.